Project update: BETL

It was painful going on Hosur Road last week. The NHAI said a pillar being erected at the Bommanahalli junction, combined with some work on the service road in the same area, had increased congestion. But it promised this work — delayed a little by the rain — will be completed soon. However, similar issues could emerge in the weeks to come as more pillars are erected.
Despite this, the PWD seems unmoved by the plea to divert heavy vehicles from Hosur Road by upgrading the road connecting Attibele junction on Hosur Road with Sarjapur Road and Dommansandra. One can see little effort to expedite the upgradation work. The work on the ramp leading into Electronic City Phase I has also begun, but will be completed after acquisition of land belonging to a company, which has raised objections.
STAGE OF WORK Piles (foundations for piers): 915 out of 1,350 done Piers: 70 out of 300 completed Underpasses: Interior work of the pedestrian underpasses at Kudlu junction and Singasandra junction is on. Block pushing for the Bommanahalli and GB Palya underpasses has begun

1 Comments:

At Tuesday, August 21, 2007 at 11:55:00 AM GMT+5:30, Anonymous Anonymous said...

Mr. Bangalorean,

Your comment: "The work ...., but will be completed after acquisition of land belonging to a company, which has raised objections."

Please comment on subjects that you have total knowledge of. Do not write out of your hat, and project your opinions / views to the world!

 

Post a Comment

<< Home